Posting Equipment Revenues

Objective

Post equipment revenue allows you to apply the costs of use for equipment to the projects on which they have been used and to charge equivalent revenues to the "equipment" projects in order to monitor their costs and revenues.

 

Ideally each piece of equipment should have its own project to allow precise tracking of the expenses (maintenance, repair, insurance, fuel, etc.) as well as the equipment’s revenue. It is also possible to track the costs and revenues of several pieces of equipment using a same project.

By "equipment" maestro*means any piece of machinery that can be used on a project. This includes small tools right up to heavy equipment.

 

Prerequisites

 

Summary

 

Steps

To post the costs of usage for equipment to a project, firstly the "equipment" project must be created, the equipment itself is created and then specify the configuration for the cost postings. Lastly, transactions must be entered in order to indicate the equipment used and the projects to which the costs are to be charged.

 

If the Preventive Maintenance module is installed and the Equipment Management option is being used to create equipment, the project can be created automatically.

 

When posting equipment revenue, the debit will be posted against the PAG (project, activity, group) identified in each transaction. The credit will be posted to the revenue PAG and to the account identified in the equipment file.

 

Create an Equipment Project

  maestro* > Projects > Maintenance > Project > Project Management

 

  1. In the section on the right, in the Project group, click on Project Management. The Project Management window is displayed.
  2. Complete the information according to the table below:

Fields

Enter / Select

Number

The project number

Description

The description of the project

Equipment

Check the box to identify this as an equipment project

  1. Complete the information in the Project Desc. tab:

Fields

Enter / Select

Start Date

The project start date

Template

Select the template to use

NOTE: If no template is selected, you will need to enter the required information in the Activities and budgets tab.

  1. Complete the information in the Parameters tab:

Field

Enter / Select

Default Equipment Rates

Equipment rate

NOTE: The rate can be selected when entering hours, however, the easiest way to indicate it is by entering which rate to use by default when creating a project.

NOTE: In Equipment Management, it is possible to enter 4 rates. This simplifies the task of selecting the correct hourly rate when entering hours.

  1. Click on Save.
  2. Click on the Activities and budgets tab, verify the assigned activities or modify if required.
  3. Click on Save, then Quit.

 

Create Equipment

Equipment management allows the creation of equipment that generates a cost of use and an internal revenue.

  maestro* > Time Management > Maintenance > Time Management > Equipment Management

 

  1. Complete the information according to the table below:

Fields

Enter / Select

Code

The equipment code

NOTE: The equipment code should represent the identification numbers, these are the numbers that will be entered into the transactions.

Status of hours entries

Active by default

NOTE: It will not be possible to enter transactions for equipment whose status is Inactive.

Name

The equipment name

Cost

Hourly rates for the equipment use

NOTE: It is possible to identify 4 hourly rates.

NOTE: It is important to have a constant for all equipment; generally rate 1 represents the use of the equipment alone. Other examples: with operator, with fuel, with operator and fuel.

Expense activity

Available Values:

Default activity

The default account for revenue clearing

Group

The default expense group

Equipment Revenue Accounting

Available Values:

Revenue Project

The project for revenue postings

Activity

The activity for revenue postings

Group

The group for revenue postings

Revenue Account

The revenue account for revenue clearing

  1. Click on Save, then Quit.

 

Configuration

Configuration allows the user to determine which GL accounts are to be automatically used when performing certain transactions and to configure the various options available.

  maestro* > Projects > Maintenance > Projects > Configuration

 

  1. In the section on the left, click on General under Projects.
  2. Complete the information in the Equipment Clearing section, according to the table below:

Fields

Enter / Select

B/S Project

The Asset project for equipment accounting

Activity

The activity for equipment accounting

Group

The expense group for equipment accounting

  1. Click on Save, then Quit.

 

The PAG used always comes from Configuration > General; therefore if this changes, it has financial implications. Manual adjustments will be necessary.

The accrued PAG should point to a general accrued transition account.

 

Hours

Enter the hours of use for the equipment on the basis of a project, an activity and a group linked to the tracking of the costs of equipment.

 

The entry of hours for equipment can be done in any of the following options: Enter Hours, Time Sheets, Work Orders and Service Management.

 

  maestro* > Time Management > Project Time > Processing > Enter Hours

 

  1. Complete the information in the Details section, according to the table below:

Fields

Enter / Select

Date

The date for the hours

Equipment

Equipment for which the hours are entered

Project-#

Project number to which the expense is assigned

Activity

Activity to which the expense is assigned

Group

Group to which the expense is assigned

Equipment Rate

Default hourly rate for the equipment.

NOTE: It is possible to select another rate.

Hours

Number of hours of use for equipment

  1. Click on Save.
  2. In the section Summary of non-transferred transactions, select the transaction to transfer the hours.
  3. Click on the Transfer button.
  4. Click on Yes.

 

The detailed hour distribution – equipment report is displayed by date, including a summary of the affected accounts.

  1. During the Transaction Transfer step, the following postings occur:

Description

Débit

Credit

Equip., Machinery (expenses)

X

 

PAG (Transit)

 

Y

  1. Click on Exit.

 

Post Equipment Revenue

The post equipment revenue allows the user to generate the GL postings linked to internal revenues calculated for the equipment. Once the equipment hours are entered, verified and transferred, the post equipment revenue can be done.

 

The Post Equipment Revenue report allows for consulting the internal revenues associated with a piece of equipment before its posting of transactions for hours transferred or not. This information is also presented at the time of posting, allowing the user to check the details prior to proceeding.

Only equipment configured for equipment revenue accounting appear on this report.

In order not to forget the posting of equipment revenue, maestro* recommends executing it at the same time as the payroll process.

 

  maestro* > Time Management > Project Time > Accounting > Post Equipment Revenue

 

  1. Complete the information according to the table below:

Fields

Enter / Select

Date Range

Dates to post equipment costs

  1. Click on Accept.
  1. Review the transactions displayed on the report. The report includes transactions for equipment hours not transferred which will be automatically transferred in the posting.
  2. Click on Yes to post the amounts.
  3. The Projects – Project to Project Transfer is displayed.

 

The income posting created by the transfer between projects will be accounted for in accordance with the selected end date.

  1. During the “Post Equipment Revenue” step, the following postings occur:

Description

Débit

Credit

PAG (Accrued Equipment)

Y

 

Equip. Revenues

 

Z

  1. Click on Exit.

 

Last modification: December 20, 2024